FOUNDATION PHASE FINISHED

You are currently viewing FOUNDATION PHASE FINISHED

The foundation to hold the container on which the experimentation prototype will be executed is ready.

The work has been carried out by the students of the second year of the training cycle of Construction Technicians as a real practice within the Professional Module 7 of Reinforced Concrete, under the direction of the professor and production manager Ramón Tor.

The foundation is made up of six 50×50 cm reinforced concrete isolated footings that support pillars made of precast concrete pieces and metal plates. The container will be raised about 30 cm above the level of the existing pavement.

Thanks to all the participants.

Staking jobs
Demolition of the hearth and excavation
Concrete of the footings
Execution of the pillars
Positioning the plates